How to register an electric meter and what is needed for this


Reasons for registering an electric meter

Electricity metering devices (MU) are reliable devices. The inter-verification period is 10-20 years. It depends on the type of meter. However, situations may arise in which it is necessary to replace the device before the end of its service life and register it.

These may be the following reasons:

  1. The expiration date has come to an end.
  2. The meter has failed. A self-propelled gun appeared or the readings stopped changing.
  3. After replacing the existing meter with a modern metering device.
  4. Changing the location of the electricity meter.
  5. There was a need for separate accounting of detached buildings. This situation arises when renting out premises for individual entrepreneurs, legal entities or individuals. In this case, a new electric meter is additionally installed.

When choosing a meter, take into account the place of its operation. Not every device has the ability to work outdoors at sub-zero temperatures.

The passport indicates the temperature indicators at which the operation of the equipment is permitted. Now the rules require that in a private house, an outdoor version of the introductory box be mounted on the wall of the building, fence or additional support.

The figure below shows a separate metering board, which doubles as an input panel on the site of a private house.

Our certificates

Cost of services

HEATING INSTALLATION
Unit measurements Cost in Moscow in rubles.
Turnkey heating system installationsq.m.520
Installation/dismantling of a heating radiator on a ready-made supply linePC.1 620
Installation of a heating radiator (with shut-off and control valves and connection to the pipeline).PC.3 420
Installation of a non-standard heating radiator (cast iron, design cast iron, design tubular).PC.4 370
Installation of an underfloor heating convector (with shut-off and control valves and connections).PC.5 420
Installation of a thermostat on a heating devicePC.245
Laying pipelines along the floor and walls d 16-32 mm.m. linear130
Laying lines along the floor and walls d 40-50 mm.m. linear170
Laying pipelines along the floor and walls d 63-110 mm.m. linear200
Laying lines along the ceiling d 16 - 32 mm.m. linear255
Laying lines along the ceiling d 40 - 50 mm.m. linear390
Laying lines along the ceiling d 63 - 110 mm.m. linear645
Installation of pipe thermal insulation for pipes d 32 mm.m. linear28
Assembly and installation of a heating manifold with connectionPC.4 560
Installation of a manifold cabinet (the built-in cabinet is mounted in a prepared niche)PC.1 190
Electric boiler installationPC.7 130
Installation of a single-circuit gas wall-mounted boilerPC.7 410
Installation of a wall-mounted double-circuit gas boilerPC.8 550
Installation of a floor-standing gas boiler up to 50 kWPC.10 260
Installation of a floor-standing gas boiler from 50 to 90 kWPC.15 390
Installation of a floor-standing gas boiler from 90 to 200 kWPC.20 240
Installation of solid fuel boiler up to 50 kWPC.11 690
Installation of a solid fuel boiler from 50 to 90 kWPC.13 680
Installation of a pellet boiler up to 50 kWPC.15 390
Installation of a pellet boiler from 50 to 90 kWPC.18 810
Installation of a diesel boiler (fuel tank, fuel pump, filters)PC.12 830
Installation of hydraulic separatorPC.3 040
Installation of the main collectorPC.4 940
Installation of a direct pump groupPC.3 420
Installation of a mixing pump groupPC.4 370
Installation of an expansion tank for a heating systemPC.1 710
Installation of a safety group for a heating systemPC.1 810
Installation of a circulation pump with an oblique filter and check valvePC.2 850
Installation of a circulation pump with bypassPC.3 800
Installation of a heat accumulator up to 400 litersPC.8 650
Installation of a heat accumulator from 400 to 1000 litersPC.12 830
Installation of boiler room automationPC.8 550
Organization of replenishment of the heating systemPC.1 330
Filling the system with coolantPC.2 850
Pressure testing of the heating systemPC.3 420
INSTALLATION OF WARM FLOOR
Installation of heated floorssq.m.420
Installation of insulation with bosses and damper tapesq.m.130
Installation of roll insulation, mesh and damper tapesq.m.180
Assembly and installation of the mixing unitPC.5 420
Installation of the mixing unit assemblyPC.2 470
Installation and assembly of a heated floor collector with connectionPC.4 560
Installation of a room heating floor controller for one circuitPC.2 700
Installation of heated floor risersPC.2 660
Installation of the control modulePC.2 850
Installation of a room thermostat with electrical wiringPC.1 430
Installation of heat distribution platesPC.45
CHIMNEY INSTALLATION
Installation of a single-wall chimney d 60 - 250 mm.m. linear720
Installation of insulated / coaxial chimney d 60 - 250 mm.m. linear1 380
Connection to a single-wall chimney d 60 - 250 mm.PC.720
Connection to an insulated / coaxial chimney d 60 - 250 mm.PC.1 380
Connection to an existing chimneyPC.2 090
WATER SUPPLY INSTALLATION
Installation of a water supply pointdot1 380
Installation of water supply risersm. linear1 660
Laying water supply pipes up to 32 mmm. linear130
Laying main water supply pipes in thermal insulation up to d 32 mm. with fasteners m. linear160
Laying an external water supply line with power supply to the pump (without excavation work)m. linear330
Installation of a water supply system collector with connection to the mains and supply pipelinePC.3 940
Installation of overhead distribution cabinet (built-in is installed in a prepared niche)PC.1 190
Pressure reducer installationPC.570
Installation and configuration of a leakage protection systemPC.5 320
Installation of a coarse filter (FGO)PC.570
Installation of a self-cleaning filter with a pressure gaugePC.1 140
Installation of terminals for heated towel railsPC.2 850
Bandaging the riser for a heated towel rail with bypassPC.3 800
Installation of a hydraulic accumulator for a water supply systemPC.2 470
Installation of a recirculation system for each groupPC.3 420
Installation of a bypass line for water treatmentPC.2 380
Installation of a pump with a check valve and a filter for the supply circuit for the boilerPC.2 190
Installation of a pumping stationPC.4 560
Well pump installationPC.5 700
Installation of a well pump with a headPC.7 130
Installation of shut-off valves at consumersPC.255
Installation of a boiler safety groupPC.1 330
Installation of a thermostatic valve for domestic hot waterPC.3 420
Installation of instantaneous water heater up to 8 kWPC.3 330
Installation of a storage boiler up to 100 l.PC.3 900
Installation of a storage boiler from 80 to 200 l.PC.6 460
Installation of an indirect heating boiler up to 150 l.PC.7 410
Installation of an indirect heating boiler 150 - 300 l.PC.8 650
Installation of an indirect heating boiler 300 - 600 l.PC.12 830
Installation of a geyserPC.5 130
Installation of caisson (without excavation)PC.6 650
Installation of a storage plastic tank up to 2 cubic meters.PC.5 600
SEWER INSTALLATION
Installation of sewage point up to 2 metersPC.720
Installation of a sewer riserm. linear860
Laying sewerage on the floor and walls, up to d 50 mm.m. linear140
Laying sewerage on the floor and walls, up to d 150 mm.m. linear285
Laying sewerage on the ceiling, up to d 50 mm.m. linear670
Laying sewerage on the ceiling, up to d 150 mm.m. linear950
Installation of a sewer check valvePC.860
Installation of sewage pumping stationPC.3 900
Installation of a sewer aeratorPC.255
Installation of a square sewer drainPC.900
Installation of a slotted sewer drainPC.2 000
Installation of sewer inspectionPC.860
Installation of TOPAS septic tank with sand bundingPC.20 900
Installation of sewer ringsPC.4 750
Laying the PND-32 pipeline with insulation without excavation workm. linear285
Laying a PVC-110 pipeline with insulation without excavation workm. linear380
Laying PVS cable without excavation workm. linear190
Installation of a drainage pumpPC.3 330
AUTOMATION OF ENGINEERING SYSTEMS
Installation and configuration of the controller (1-2 control outputs)PC.3 420
Installation of a boiler and heating control controllerPC.11 120
Installation and adjustment of a mechanical thermostatPC.950
Installation and adjustment of an electric thermostatPC.1 330
Installation and adjustment of a weekly thermostatPC.1 800
Installation of a thermostat for a trench convector with forced convectionPC.3 420
Installation of a pressure switch with alarmPC.3 140
Installation of a pump pressure switchPC.1 800
Organization of protection of the dry passage of the nosePC.3 420
Installation of a boiler outdoor temperature sensorPC.1 800
Installation of a boiler temperature sensorPC.950
Installation of three-way valve servomotorPC.950
Installation of commutator servo drivePC.950
Installation of boiler room electrical panelPC.4 750
Installation of a flow switchPC.3 040
Installation of frequency automation on the pumpPC.3 040
Electrical connection of the boiler and circulation pumpPC.1 140
Installation of pump automationPC.2 000
Laying a heating cable without excavation workPC.2 850
Electrical connection of the solenoid valvePC.950
Electrical connection of the temperature relayPC.950
Assembly of the automation control panelPC.42 750
PLUMBING WORK
Installation installationPC.3 420
Installation of hydromassage panelPC.5 130
Installation of a steel / acrylic bathtubPC.3 700
Installation of a cast iron bathtubPC.4 700
Installing a whirlpool bathPC.7 600
Installation and assembly of a shower cabinPC.5 700
Installation and assembly of a shower cabin with hydromassagePC.6 900
Washing machine/dishwasher installationPC.1 140
Installing a water heated towel rail without changing the connection diagramPC.1 620
Installation of an electric heated towel railPC.1 140
Installation of an overhead sink (without mixer and siphon)PC.670
Installing a sink on bracketsPC.950
Installation of a sink with a “Tulip” standPC.1 430
Installation of a sink with a cabinet-underframe “Moidodyr”PC.2 850
Installation of toilet, bidetPC.2 570
Toilet assemblyPC.480
Installation of a wall-mounted mixer with eccentricsPC.1 140
Installing a shower rodPC.760
Installation of a shower column (rain shower)PC.2 380
Installation of a concealed mixerPC.4 750
Installing a faucet on a washbasinPC.950
Installation of bidet mixer with hygienic showerPC.1 430
Mixer assemblyPC.240
Installation of corner tap with reflectorPC.330
Installing a siphon on a sinkPC.480
Installing a siphon on a bathtub with pipingPC.670
Installing a siphon on a bathtub (automatic piping)PC.860
Installing a siphon on a bathtub (copper, steel piping)PC.950
Installation of toilet corrugationPC.670
Siphon assemblyPC.190
Installation of a food waste shredderPC.1 900
Installation of a fine filter (AQUOPHOR, GEYSER)PC.2 280
Installation of a household reverse osmosis purification systemPC.3 900
Replacing filter cartridgesPC.950
Installation of flexible linerPC.140
Sealing seams with siliconePC.180
Punching a hole in the sink for the faucetPC.350
REPLACEMENT / INSTALLATION / MAINTENANCE OF METERING DEVICES
Checking the water meterPC.1000
Replacing a water meter (work)PC.1000
Installation of a water meter (work)PC.1 430
Commissioning of a DHW and cold water metering devicePC.1 400
Sealing of the metering devicePC.500
Replacing the connecting kit (American) with a check valvePC.670
Ball valve installationPC.330
Installing/Replacing a Check ValvePC.570
Cleaning the coarse filter (FGO)PC.460
Eliminating leaks (replacing gaskets)PC.380
Installing an aerator to save waterPC.280
REPAIR AND SERVICE
Diagnosis of boiler, heating and water supply system malfunctionsPC.2 850
Boiler, heating and water supply system repair (simple breakdown)PC.4 750
Repair of boiler, heating and water supply systems (complex breakdown)PC.7 600
Replacing the expansion tankPC.4 280
Replacing the circulation pumpPC.3 800
Replacing a three-way mixerPC.4 750
Replacing the servoPC.2 850
Replacement of air vent, valve, pressure gauge, thermometer, thermomanometerPC.860
Replacement of ball valve, oblique filter, check valvePC.950
Draining and filling coolant into the heating systemPC.7 600
Flushing the heating systemPC.17 100
Flushing the boiler heat exchangerPC.6 200
Boiler servicePC.8 550
DISMANTLING WORK
Dismantling the boiler without removalPC.2 380
Dismantling the boiler without removalPC.2 380
Dismantling a heating radiator without removalPC.480
Dismantling of pipes d 15 - 25 mm.PC.100
Dismantling of sewer pipes d 50 mm.PC.380
Caulking a cast iron sewer pipePC.1 140
Dismantling a steel / acrylic bathtub without removalPC.950
Dismantling a cast iron bathtub without removalPC.1 140
Dismantling a shower cabin without removalPC.1 430
Dismantling the sink/sink with underframePC.570
Dismantling the toiletPC.480
Removing a washing machine/dishwasherPC.480
Removing the heated towel railPC.480
Removing the shower panel with hydromassagePC.670
Removing the sink/sink/tub faucetPC.380
Removing the sink/sink siphonPC.280
Removing the bathtub trimPC.380
DESIGN
Drawing up a room plansq.m..30
Thermal engineering calculation (floor height up to 4 m)sq.m.30
House heating project up to 100 m2PC.14 250
House heating project from 100 to 500 m2sq.m.85
Project for heating a house from 500 m2sq.m.70
Design of a water heated floor systemsq.m.75
Water supply project up to 100 m2PC.11 400
Water supply and sewerage project for a house from 100 to 500 m2sq.m.75
Water supply and sewerage project for a house from 500 m2sq.m.65
Integrated design of home systemssq.m.120
DRILLING WALLS FOR PIPES
Concrete (diameter up to 25 mm.)m.p.570
Brick (diameter up to 25 mm.)m.p.380
Gypsum (diameter up to 25 mm.)m.p.280
Concrete (diameter from 25 mm to 50 mm)m.p.760
Brick (diameter from 25 mm to 50 mm)m.p.570
Gypsum (diameter from 25 mm to 50 mm)m.p.380
General types of work
Pipe cutting: polypropylene, metal plastic, PVC sewer*PC.50
Installation of metal and rubber clamps*PC.110
Installation of angles, couplings, tees - one connection*PC.180
Removing sewer clogsPC.1900
Cleaning a solo elevatorPC.3800
Fixing a leak under the bathtubPC.1140
Eliminating siphon leaks under the sink, cleaning the siphonPC.670
Installing the comb on the bracketsPC.760
Additional thread cuttingPC.140
Installation of a sanitary hatch 40cm*40cm with site preparationPC.2380
Other works
Works, services not included in the price listone hour600
Visit of a specialist to prepare an estimateone0
Removal of technical waste and pipes0

Requirements for metering devices

The choice of device should be approached responsibly. It is necessary to select the type of device that is in the list of the state register of measuring instruments. In this case, the electricity meter must be approved by the federal executive body for technical regulation and metrology.

PU must meet the operating conditions at the installation site. Have an error of no more than 2%. The owner must decide what power will be installed in the premises.

Select an electric meter by type of design:

  • Mechanical single-phase. These devices are not currently produced, but you can still find them in the retail chain. You should avoid purchasing such devices. They are morally outdated.
  • Electronic devices. Compact, inexpensive PU. Meet all necessary requirements. Accuracy class 1-0.5%. Both single-phase and three-phase options are available. They have the ability to transmit data over communication lines or via the Internet. They can be single-tariff or multi-tariff.

The owner chooses which electric meter to purchase. But it should be taken into account that the equipment must be connected to the network by an electrician from a specialized organization that has certificates for performing similar work. If the owner makes the connection himself, he will be fined for illegal connection.

But, before calling a specialist to register the meter, it is necessary to inspect the input panel and machines. Bring equipment into compliance with standards. If the connection is made at a summer cottage, it is recommended to purchase a ready-made mounted panel. This will save the owner from unnecessary expenses.

Time to put the electric meter into operation

Based on the current rules for the provision of utility services to citizens, the consumer must send an application to fix the date and deadline for putting the new meter into operation.
The appeal must be considered by the energy saving company as the executor.

If the time indicated by the consumer in the application is busy and it is problematic to allocate it, the executor may send an appeal to the applicant with a request to revise the date.

Consideration of an application from a citizen should not last more than three days. In addition, it is prohibited to offer the applicant a date that postpones the requested date by more than 15 days.

It is important to pay attention! If the contractor does not appear at the site within the time period established in the application or he cannot offer an alternative date in less than 15 days, then the device will be considered put into operation.

The registration date will be the exact day on which the citizen submitted the application. All indications for payment of electricity consumption will be counted from this moment. If the energy saving company continues to charge payments according to average consumption standards, the user has the right to file a complaint with the Housing Inspectorate.

Documents required for registration

After connecting the control unit to the power grid, which is carried out by a specialized organization, the owner submits an application to the power supply. It is important to note that the company must have a license to carry out such work.

Before the visit, he collects a package of documents, which includes:

  • A statement that is written directly at the energy sales office. A sample is provided upon request. It contains information: last name, first name, patronymic of the owner, passport and contact information. Indicate the desired date of registration. Type of device, serial number of the electric meter. They are indicated in the passport for the electric meter. Data from the company that connected the device to the network. And the readings at the time of connection;
  • Copies of documents on the basis of which the form is filled out are attached to the application.

What if I want a smart electricity meter right now?

If your electric meter was installed recently and there are still 10-16 years left until the end of the calibration interval, it makes sense to check with the energy sales company when they plan to replace the meters. Energy engineers may be planning automation in the near future, then you will just need to wait a little until it’s your turn to reach your apartment.

If you plan to install smart meters only after the verification interval has expired, and you want to get rid of the need to transfer readings every month, it makes sense to install a smart electric meter at your own expense.

Metering device registration deadlines

After submitting the application, registration of the electric meter must be completed no later than 30 days from the date of submission of the application.

If the inspector does not come within 15 days after the appointed time, it is considered that the electricity meter has been put into operation.

The owner should know that after installing the seal, a report must be drawn up. When replacing an old meter with a new one, the report indicates the latest readings of the previous device. The act must be registered in a single center.

Who pays for the meter replacement?

The cost of installing and registering a new meter depends on the type of property ownership. If the apartment is privatized, the owner is obliged to maintain electrical appliances. All expenses are paid by the property owner.

For municipal housing, work is performed not at the expense of the owner, but of the person renting the apartment. It is he who will have to purchase a new meter and bear the costs of installation and registration.

We recommend: How to correctly calculate gas payments


Registration procedure

The installed electric meter must be registered (registered) with the energy supply company. The registration procedure is carried out in the following order:

  • the owner applies to the energy supplier with an application to register the meter;
  • within a week from the date of filing the application, the organization makes adjustments to the state register;
  • at the next stage, a resolution on registering a new meter is signed;
  • the applicant is issued a certificate for the purchase of the device;
  • Based on the document received, an electric meter is purchased.

Complete with the purchased product, the owner receives a device passport issued by the manufacturer. The owner is obliged to keep the certificate and passport of the meter issued by the resource supplier for the entire period of operation of the device, since this documentation indicates the main technical characteristics of the product.

Can the management company pay for the installation of smart water, gas or heat meters?

Maybe if such a decision is made by a general meeting of home owners, but in practice such situations are rare. The initiator of consideration of the issue of automation at a general meeting can be the management company itself or the residents of the apartment building.

A positive decision will certainly be beneficial to the management company, because it will reduce both the amount of operational work for collecting evidence and the number of defaulters. In turn, residents will be freed from the need to submit their testimony monthly and pay for unreliable neighbors. But in any case, residents will finance the installation of smart appliances, so the decision to use them within an entire house or community is always made collectively.

Rating
( 2 ratings, average 5 out of 5 )
Did you like the article? Share with friends:
For any suggestions regarding the site: [email protected]
Для любых предложений по сайту: [email protected]